Patel and another v Peters and others – WLR Daily

Patel and another v Peters and others [2014] EWCA Civ 335; [2014] WLR (D) 147

‘Where the surveyor of a party involved in a dispute over building works affecting adjoining properties served a request under section 10(7) of the Party Wall etc Act 1996 on the surveyor of the other party that he act effectively in respect of the subject matter referred to in the request within ten days, after which, if he did not so act, the requesting surveyor became entitled to act ex parte in respect of the matter, a continuing state of affairs was created so that the other party’s surveyor might still act effectively after that ten-day period, thereby precluding the requesting surveyor from acting ex parte, provided that the requesting surveyor had not yet proceeded so to act.’

WLR Daily, 27th March 2014

Source: www.iclr.co.uk