RTS Flexible Systems Ltd v Molkerei Alois Müller Gmbh & Co KG (UK Production) [2010] UKSC 14; [2010] WLR (D) 75
“A draft contractual agreement to install equipment in a factory, which was never executed as the work was commenced, completed and partly paid for during the negotiations, took effect as a binding contract as the essential terms had been agreed and neither party had intended agreement of the remaining terms to be a precondition to a concluded contract. Although the draft agreement contained a clause stating that the contract was not effective until it was executed, it was possible for parties to waive such a clause and, on the facts, these parties had done so.”
WLR Daily, 11th March 2010
Source: www.lawreports.co.uk